Muck away calculator: loads, tonnes and cost for your dig

By the Plant & Haul team · Checked

In November 2026, an 8-wheel grab load costs about £260–£450 and takes about 10–12 m³ or 16 tonnes, whichever comes first. Dug soil takes up 20–30% more room than in the ground, and one m³ of dug soil or clay weighs about 1.3–1.8 tonnes.

Get real quotes for this jobFree, no account needed. Matching suppliers call or WhatsApp you.

Sources and dates: end of this guide.

Work out how many grab lorry loads, cubic metres and tonnes your dig makes, and roughly what it costs to take away, for soil, clay, rubble or sand.

How the calculator works

Enter the length, width and depth of the dig in metres and say what it is. The calculator adds the 20–30% that material swells by once it is dug, works out the weight, and counts 8-wheel grab loads by room (about 10–12 m³) and by weight (about 16 tonnes), whichever runs out first. The cost uses £260–£450 a load from the UK price lists in our muck away cost guide.

Muck away calculator: how many grab loads?

Measure the dig in metres and say what it is. The calculator allows for material taking up 20–30% more room once it is dug, and for an 8-wheel grab lorry holding about 10–12 cubic metres or about 16 tonnes, whichever comes first.

About 1–2 grab loads, roughly £260–£9007.5 m³ in the ground becomes about 9–9.8 m³ once dug, weighing about 11.7–16.6 tonnes, so the lorry fills by weight before it is full. By room, that would fill about 2 8-yard builder's skips.

Cost uses £260–£450 a load for an 8-wheel grab, from the UK price lists in this guide. Wet clay, rubble and mixed or green waste weigh more or cost more to tip, and a lorry may be full by weight before it is full by volume. Operators quote the real price.

Get real quotes for this jobFree, no account needed. Matching suppliers call or WhatsApp you.

What dug material weighs

Weights of one cubic metre once dug, from material tables and suppliers, read in November 2026.

What dug material weighs
MaterialTonnes per m³Swells by about
Soil or topsoil1.3–1.720–30%
Clay1.6 dry, about 1.8 wet20–40%
Sand1.6 dry, 1.9 wet10–30%
Gravel1.7 dry, 2.0 wet12–30%
Crushed concrete and brickAbout 1.6Up to about 67% as broken rubble

Swell is how much more room material takes up once it is dug out of the ground. Wet material is heavier: after rain, expect fewer cubic metres a load.

What one load holds

Published by one grab hire firm (Recycle Southern, West Sussex), with typical figures from others:

What one load holds
Grab lorryRoomWeight
4-wheelAbout 9 m³About 7 tonnes
6-wheelAbout 13 m³About 10–12 tonnes
8-wheelAbout 12–15 m³About 16 tonnes

See grab lorry sizes for access width, height and reach.

Worked examples

  • A 5 × 3 m patio dug 0.5 m deep (7.5 m³ of soil or topsoil in the ground): about 9–9.8 m³ once dug, about 12–17 tonnes. 1–2 loads of an 8-wheel grab lorry, about £260–£900.
  • A 10 × 4 m extension footprint dug 1 m deep (40 m³ of clay in the ground): about 48–52 m³ once dug, about 77–92 tonnes. 5–6 loads of an 8-wheel grab lorry, about £1,300–£2,700.

Questions

How many tonnes is a cubic metre of soil?

About 1.3–1.7 tonnes once dug, and more when wet. Clay is about 1.6–1.8 tonnes, crushed concrete and brick about 1.6.

How many grab loads is my dig?

Measure it in metres, multiply length × width × depth, and add 20–30% for swell. An 8-wheel grab takes about 10–12 m³ or 16 tonnes a load, whichever comes first. The calculator above does the sum.

Is muck away priced per tonne or per load?

Most grab hire firms price per load; some price per tonne (about £15–£45 a tonne for inert soil and rubble in November 2026). Ask which, and whether tipping and VAT are included.

Sources, checked 15 November 2026

Prices as each page showed them on the day we read it. Plant & Haul sets no prices.