Muck away calculator: loads, tonnes and cost for your dig
In November 2026, an 8-wheel grab load costs about £260–£450 and takes about 10–12 m³ or 16 tonnes, whichever comes first. Dug soil takes up 20–30% more room than in the ground, and one m³ of dug soil or clay weighs about 1.3–1.8 tonnes.
Get real quotes for this jobFree, no account needed. Matching suppliers call or WhatsApp you.
Sources and dates: end of this guide.
Work out how many grab lorry loads, cubic metres and tonnes your dig makes, and roughly what it costs to take away, for soil, clay, rubble or sand.
How the calculator works
Enter the length, width and depth of the dig in metres and say what it is. The calculator adds the 20–30% that material swells by once it is dug, works out the weight, and counts 8-wheel grab loads by room (about 10–12 m³) and by weight (about 16 tonnes), whichever runs out first. The cost uses £260–£450 a load from the UK price lists in our muck away cost guide.
Muck away calculator: how many grab loads?
Measure the dig in metres and say what it is. The calculator allows for material taking up 20–30% more room once it is dug, and for an 8-wheel grab lorry holding about 10–12 cubic metres or about 16 tonnes, whichever comes first.
Cost uses £260–£450 a load for an 8-wheel grab, from the UK price lists in this guide. Wet clay, rubble and mixed or green waste weigh more or cost more to tip, and a lorry may be full by weight before it is full by volume. Operators quote the real price.
Get real quotes for this jobFree, no account needed. Matching suppliers call or WhatsApp you.
What dug material weighs
Weights of one cubic metre once dug, from material tables and suppliers, read in November 2026.
| Material | Tonnes per m³ | Swells by about |
|---|---|---|
| Soil or topsoil | 1.3–1.7 | 20–30% |
| Clay | 1.6 dry, about 1.8 wet | 20–40% |
| Sand | 1.6 dry, 1.9 wet | 10–30% |
| Gravel | 1.7 dry, 2.0 wet | 12–30% |
| Crushed concrete and brick | About 1.6 | Up to about 67% as broken rubble |
Swell is how much more room material takes up once it is dug out of the ground. Wet material is heavier: after rain, expect fewer cubic metres a load.
What one load holds
Published by one grab hire firm (Recycle Southern, West Sussex), with typical figures from others:
| Grab lorry | Room | Weight |
|---|---|---|
| 4-wheel | About 9 m³ | About 7 tonnes |
| 6-wheel | About 13 m³ | About 10–12 tonnes |
| 8-wheel | About 12–15 m³ | About 16 tonnes |
See grab lorry sizes for access width, height and reach.
Worked examples
- A 5 × 3 m patio dug 0.5 m deep (7.5 m³ of soil or topsoil in the ground): about 9–9.8 m³ once dug, about 12–17 tonnes. 1–2 loads of an 8-wheel grab lorry, about £260–£900.
- A 10 × 4 m extension footprint dug 1 m deep (40 m³ of clay in the ground): about 48–52 m³ once dug, about 77–92 tonnes. 5–6 loads of an 8-wheel grab lorry, about £1,300–£2,700.
Questions
How many tonnes is a cubic metre of soil?
About 1.3–1.7 tonnes once dug, and more when wet. Clay is about 1.6–1.8 tonnes, crushed concrete and brick about 1.6.
How many grab loads is my dig?
Measure it in metres, multiply length × width × depth, and add 20–30% for swell. An 8-wheel grab takes about 10–12 m³ or 16 tonnes a load, whichever comes first. The calculator above does the sum.
Is muck away priced per tonne or per load?
Most grab hire firms price per load; some price per tonne (about £15–£45 a tonne for inert soil and rubble in November 2026). Ask which, and whether tipping and VAT are included.
Sources, checked 15 November 2026
- Engineering ToolBox: dirt and mud densities
- Engineering ToolBox: soil and rock bulking factors
- Spike's Calculators: bulking and swell factors
- Topsoil Shop: topsoil calculator
- Mainland Aggregates: 6F2 recycled capping
- Recycle Southern: grab hire prices and lorry sizes, West Sussex
- WasteKing: grab hire services
- J9 Aggregates: muck away, West Midlands
- Checkatrade: grab hire cost (last updated May 2024)
- James Grab and Tipper Hire: grab hire and muck away prices, South Wales
Prices as each page showed them on the day we read it. Plant & Haul sets no prices.
Read next
- Muck away cost per load, and a calculator for your digWhat muck away costs per load for soil, clay, brick and green waste, why the material matters so much, and how many loads your dig will make.
- Grab lorry sizes: how many tonnes does a grab lorry take?What a 4, 6 and 8-wheel grab lorry carries in tonnes and cubic metres, how far the grab reaches, and how much width and height it needs to get in and work.
- Grab hire vs skip hire: which is cheaper for your job?Grab lorry or skip? Prices per load and per skip size, the cost per cubic metre, a worked example, the permit a skip on the road needs, and when each one wins.